website dev on hold cause i am waiting for texts/images.

client: why i dont hear from you. site will launch on oct. 1st.(real: late oct.)

me: on hold tull i get those things from you as we said in mid aug.

client: i am really pissed of. you got 90% of the stuff so work with it.

the thing is im waiting for some images to create the design. now i am really pissed of. hate clients that wanna tell you how to make your job. what would you do?

Comments
  • 3
    Plan A: don't start production until you have what you need.
    Plan B: don't start the next milestone until you have what you need.
    Plan C: down tools, work on something else until you have what you need.
    Plan C+: suggest they hire/budget for a photographer/copywriter to get you what you need.

    Job done :)
  • 3
    Plan D: climb into his ass, get the project done in 1 week without the stuff ( lower quality ), get my money and tell him fy.
  • 3
    Set deliverable dates for the client. If they do not adhere to the dates that's their problem.