Ok so there is this company we work for as a client. They stalled the project for 3 months not wanting to sign the contract in the summer for reasons unknown while we "waited" to start.

In the contract it was noted that the project will take 6 months FROM THE time they sign the contract.
They signed it in September and still want to go live this year. They don't care what is in the contract but they have legal deadlines they must comply and for that they need the project.
I mean WAT? How disfunctional you must be to stall a project you have legal compliance for?

Comments
  • 3
    Sucks for them, I guess. I wouldn't do it unless they sign a new contract and pay at least triple. You got them by the balls now.
  • 1
    In reality, I think client must have to change the MVP to make client still happy. There's nothing else you can't do. Extra team members on short term cost time.

    Even when it's not in contract, clients dick have to be sucked often, else you're out of business in no time.

    Yh, disfunctional indeed 😁